For Six Months You Could Have Driven Past This Lot and Thought Nothing Was Happening

By Farbod Fatahi · November 2026

For six months you could have driven past our Old Yonge lot in North York and thought nothing was happening. Then, in one week in October, the whole house came down. Tearing a house down is the fast part. This is what the months before it were for, and what they mean if you're planning to build a custom home in Toronto.

How it ran on Old Yonge:

  • Spring: design begins. Where the house sits on the lot, how it works, what the clients need from it.
  • End of July: the Committee of Adjustment approves the variances, on the first application.
  • End of September: the building permits come through.
  • October: demolition, then excavation.

The general rule: from a first conversation to permits in hand is about five to six months of work on average. The Committee of Adjustment alone adds two to four months at minimum, and most homes need it now.

What that means for you: if you're thinking about starting your build in the spring, you need to start planning now. None of this work happens on site, so it's the part nobody sees, but it decides whether you're digging in the spring or still waiting on paperwork in the summer.